Project overview

Organisation: NHS Greater Glasgow & Clyde 
Hospital: Inverclyde Royal Hospital
Project
: Partial upgrade of Fractures Clinic
Value: £118, 000
Timescale: 10 weeks

Project specifics:

  • Doors and floors to be upgraded to selected areas
  • Phased approach to maintain operational requirements pathway of care for patients
  • Strategic co-ordination of patients and stakeholders
  • Infection control measures carefully measured

Partial Upgrade of Fractures Clinic - IRH

This project, over 10 weeks, was to partially upgrade doors and floors within this extremely busy and crucial department.

The main and vital consideration was how to operationally maintain the pathway of care and consultation within this department whilst carrying out the upgrade works.

Working effectively with user management on a multi phased approach with protective screening around active construction areas was difficult but effective and productive communication over the whole period ensured that the project was completed to the satisfaction of all and without any issues occurring.