Project overview

Organisation: NHS Greater Glasgow & Clyde
Hospital: Glasgow Dental Hospital
Project
: General Infrastructure Projects
Value: £3.2 million
Timescale: 2010-2013

Project specifics:

  • Upgrading of ventilation units
  • Installation of generator
  • Major electrical infrastructure upgrade
  • Major drainage and hot and cold water upgrade
  • Extremely restricted working area
  • Sensitive co-ordination with all staff teams 

General Infrastructure Projects - GDH

Elements that were managed were as follows:

  • Upgrading of air handling ventilation 
  • Installation of stand –by generator
  • Installation of a water filtration uniit
  • Installation of medical gas store
  • Installation of replacement distribution boards

Problems that arose were associated with:

  • Existing electrical Infrastructure.
  • Existing mechanical control.
  • Infection control.
  • Associated dated mechanical infrastructure
  • Maintaining operational aspects within the hospital as a whole whilst works were being carried out

Delicate co-ordination was essential with all hospital management including:

• Facilities
• Estates
• Infection Control
• Theatre operational staff
• Health & Safety
• Fire Advisor