Project overview

Organisation: NHS Greater Glasgow & Clyde
Hospital: Gartnavel General Hospital
Project
: Theatre Ventilation Systems upgrade
Value: £400, 000
Timescale: 2 durations of 10 weeks

Project specifics:

  • Removing and upgrading ventilation units
  • Complex management of aged existing services
  • Delicate Mechanical & Electrical design
  • Specialist consideration of clinical air flow and control systems

Ventilation Upgrade - GGH

Project works were carried out of over 2 NHS financial years over 2 No durations of 10 weeks.

The purpose was to remove existing and upgrade major ventilation units within above Theatre clinical areas.

Effective coordination contributed towards the success of the projects, although some aspects did introduce concern when connecting to existing services, which were aged and dilapidated.

Mechanical and Electrical design was extremely delicate and intense at all stages of the project with specialist considerations within various aspects such clinical air flow and control systems.

Total Contract value was £400,000.00